Cariboo Gold Construction Reaches About 28%; Osisko Holds to First Gold in Q1 2029

Osisko Gold Group Inc. (NYSE: OGG, TSXV: OGG) says its Cariboo Gold Project near Wells is about 28% complete and still on schedule for a first gold pour in the first quarter of 2029 and commercial production in the second half of 2029.

The company says about $355 million had been spent to September 30, including about $84 million in August and September, with an estimated $907 million left to complete construction. Detailed engineering is about 42% complete and more than half of the procurement packages have been awarded, representing about $360 million in commitments. More than 400 people are now working on site.

Recent progress includes Valley Portal earthworks at 85%, the Bonanza Ledge waste rock storage facility (Phase 1a) at 95%, and the Bonanza Ledge water treatment plant expansion built, with commissioning under way. About 3.4 km of underground development has been completed. Osisko now expects development rates of about 360 m a month by the end of 2026, down from 500 m a month previously, citing slower progress at the Valley portal.

Osisko made its formal decision to build the project on September 14, 2026.

Source: Osisko Gold Group Inc. news release, October 27, 2026 (GlobeNewswire). Read the full release.