Artemis Provides Interim Results of Grade Control Drilling of High-grade Near Surface Mineralization

, , , , , , ,

Vancouver, British Columbia – May 4, 2021 – Artemis Gold Inc. (TSX-V: ARTG) (“Artemis” or the “Company”) is pleased to provide an update to its Grade Control drilling program (the “Program”) that commenced in Q4 2020 targeting the planned high-grade starter pit at the Company’s Blackwater Gold project in Central British Columbia, Canada (“Blackwater” or the “Project”).

To date, results from the Program provide significantly increased confidence in the target area earmarked for the first year of operations at Blackwater compared with the corresponding area in the Company’s mineral resource estimate as contained in the Company’s 2020 PFS (defined below). The program confirmed wide, near surface intersects of elevated gold grades at the start of the mine life as outlined in the 2020 Pre Feasibility Study for Blackwater (“Blackwater Gold Project British Columbia NI 43-101 Technical Report on Pre-Feasibility Study” with an effective date of August 26, 2020, available on the Company’s website and on SEDAR at www.sedar.com (“2020 PFS”)).

The Program was designed to bring the drill density from up to 50 x 50m core spacing down to 12.5 x 12.5m spacing, generating up to 16 times the data when compared to the New Gold reserve definition drill program. This Program has targeted a zone within the first 60 m (six mining benches) from surface containing in excess of five million tonnes of high-grade ore to improve short-term mine planning at the start of production.

The other primary objectives of the Program were to:

  • Optimize the grade selectivity and mine schedule for managing the ore tonnes and grade to be processed in the first year of operations;
  • More accurately delineate ore and waste boundaries to mitigate dilution;
  • Optimize drill and blast designs;
  • Provide a larger sample size to reduce grade variability.

Summary of Selected Grade Control Drilling to Date

The Program consisted of 561 holes and 33,216 m of reverse circulation (“RC”) drilling, which commenced in mid-November 2020 and concluded at the end of March 2021, one month ahead of schedule.  

The associated assaying work is ongoing, with all samples dispatched for analysis to SGS Canada Inc. (“SGS”) in Burnaby, B.C. To date, a total of 9,286 assays or approximately 75% of the total samples dispatched have been returned, confirming the planned high-grade early mining phase for Blackwater (see attached Figure 1). Selected results from the Program are highlighted below:

Table 1: Near-Surface Intercepts from Grade Control Drilling Program1

Hole ID*EastNorthFrom (m)To (m)IntervalAu (g/t)**Ag (g/t)**
BWRC00088375612.558927502139189.323.8
BWRC0010137545058927502439156.712.8
BWRC001103756005892762.51863455.611.1
incl.  1821330.518.7
BWRC00119375487.55892762.534239410.5
BWRC001223754505892762.5345423.712.7
BWRC001473754005892775333303.55.6
BWRC00157375537.55892787.533663310.412.7
incl.  4551639.436.3
BWRC0017937557558928002145245.99.3
BWRC00180375562.558928002754275.89.5
BWRC00190375437.5589280018392112.412.2
incl.  2124343.229.2
BWRC001933754005892800918911.411.5
incl.  912322.511.9
BWRC002503752505892812.5660543.27.1
BWRC00251375237.55892812.52160396.510.8
incl.  5154326.412.3
BWRC0025937570058928256363044.2
BWRC0026537562558928254554912.131.5
incl.  4851321.557.2
BWRC0026737560058928252148276.814.8
BWRC00280375437.5589282548601212.615.5
incl.  5154324.925.8
BWRC00297375225589282545601511.936.4
incl.  5457330.872.3
BWRC00298375212.5589282542601848.712
incl.  5760321.921.4
BWRC00319375512.55892837.524512712.516.7
incl.  3942358.554.3
BWRC003443752005892837.53357247.96.3
incl.  4548321.215.1
BWRC0035737560058928503042129.968.7
BWRC00389375200589285045571213.812.2
incl.  5154327.513.9

* All holes were drilled with a dip of -90º (vertical). Drill hole intercepts reflect minimum 70% of the true widths of the orebody. Only intercepts greater than 9 m of length and width x grade greater than 100 g–m of gold are reflected in this news release. 
** Assay results are based on the leached Au and Ag after 5-hour LeachWELLTM accelerated leach, and exclude Au and Ag remaining in residue solids.


1 Refer to notes 1, 2, and 3 within the section entitled ”Technical Disclosure” at the end of this press release

The LeachWELLTM assay method was selected to increase the sample size from a more standard 50g to one kilogram sample which reduces variability and increases repeatability of assay results. Additionally, the LeachWELLTM method increases the understanding of leachability of the orebody with the information feeding directly into the process design. Extensive duplicate analyses highlight excellent LeachWELLTM repeatability of assay results and recoverable gold and silver.

To date, 849 samples were assayed for residue gold and silver concentration in the LeachWELLTM residues, resulting in a calculated overall recovery of 96.7% for gold and 72.2% of silver.

The Program has also confirmed excellent continuity of mineralization, based on available assay results, as illustrated in the sections provided in Figures 3-8.  The location of these sections is provided in Figure 2.

A further update on the grade control drilling results and conclusions will be provided later in Q2 2021 once all final assay results have been completed and interpreted by the Company.

Steven Dean, Chairman and CEO commented “These initial results from the grade control drilling program indicates the potential for more tonnage and more contained ounces within the high-grade starter zone, which could also potentially reduce the strip ratio at the beginning of the mine life.  The grade control drilling program at Blackwater is similar to the practice successfully applied at Atlantic Gold, providing substantially more data to optimize mine planning. This program is also designed to further demonstrate the strong continuity of high-grade mineralization at the start of the mine life and provide a higher confidence level in the Phase 1 mining schedule outlined in the Company’s 2020 Pre-Feasibility Study, further derisking the start up of operations. This data will be incorporated into the mine plan in the upcoming Definitive Feasibility Study to be issued mid-2021.

Technical Disclosure

Drill sampling consisted of reverse circulation drill cuttings being collected at a drill mounted Metzke rotating cone splitter by Artemis personnel on 3 m intervals. Samples were placed into bags and further split at the Blackwater sampling facility to ~3 kg sample size using a jones riffle splitter. Samples were tagged with barcodes, placed in a sample crate and a laboratory dispatch form was completed. Samples were stored in a secure location prior to shipping. Chain-of-custody procedures consisted of filling out sample submittal forms that were sent to the laboratory with sample shipments to make certain that all samples were received by the laboratory. 

Sample preparation and analysis were performed by SGS Canada Inc. (“SGS”), located in Burnaby, British Columbia, Canada. SGS holds ISO/IEC accreditation for selected sample preparation and analytical techniques and is independent of the Company.  Sample preparation consisted of drying, crushing and pulverizing to 75% passing 75 µm.  Gold and silver analyses were performed using a 5-hour 1,000 g LeachWELLTM method with an inductively coupled plasma mass spectrometry finish (ICP-MS).

The representativeness of the LeachWELLTM analytical technique to a mineral deposit is dependent on the leaching characteristics of the material submitted. As no certified standard reference material had been prepared from the same material that was to be leached, no standard reference materials were inserted in the grade control sample stream to directly monitor analytical precision. Precision checks consisted of comparisons to results from split samples using 50 g fire assay methods, comparison of data to existing diamond drill holes and review of SGS laboratory standards. Additionally, LeachWELLTM tails solids were consistently checked for non leachable gold and silver using 50 g fire assay for gold and 2 g 4-acid digestion for silver. The Company randomly inserted blank and duplicate samples into the sample stream as part of the quality assurance and quality control (QA/QC) monitoring for the Program at an insertion rate of ~10%. These samples had closely monitored contamination, splitter functionality and analytical repeatability, respectively.

Mr. Klaus Popelka (Qualified Person) reviewed the available Program data, and considers that the sample preparation, security, and analytical procedures are acceptable. There are no drilling, sampling or recovery factors known to the QP that could materially impact the accuracy and reliability of the results presented in this news release.

Qualified Persons

Klaus Popelka, P. Geo., Manager Resource Geology for Artemis, and a QP as defined by National Instrument 43-101, has reviewed, and approved the scientific and technical information in this news release.

ARTEMIS GOLD INC.
On behalf of the Board of Directors

“Steven Dean”
Chairman and Chief Executive Officer
+1 604 558 1107